In their weekly Friday at midnight newsletter, Midnight Trains have announced it their “death”. The French company wanted to start a ‘hotel on rails‘ upscale night train service linking the United Kingdom and the European continent.
Back in June 2021, a company in France called Midnight Trains launched its âhotel on railsâ project for luxury night train services worthy a hotel experience. Every Friday, Midnight Trains sent a newsletter with some sort of update on its project. These updates outlined the challenges the team faced. In the night of the 31st of May to the 1st of June 2024, Midnight Trains announced the end of a dream.Â
The obituary reads as an honest analyses of strengths and weaknesses and is a reality check for those who think (re)launching night train services is self-evident cause.
Midnight Trains died today, surrounded by family and friends.
We have done everything in our power to succeed in making the shared dream of a 21st century night train come true. It was a beautiful, worthwhile night train that had the power to make sustainable travel between Europeâs major cities a reality.
Today is the end of an ambitious project launched by a bold trio. For four years, weâve put all our energy into reinventing the night train to make it a mode of transport thatâs in tune with our times, able to compete with medium-haul aviation and offers a desirable alternative to all those who wish to continue travelling, without trashing the planet.
It was a crazy gamble, but not that crazy. Over the last decade, European railway infrastructures have gradually opened up to all public or private operators wishing to run trains. Before then, it was only national operators (SNCF, Renfe, DB, etc.) who did so. The regulatory framework opened its arms to us. Some european achievements â Italo, Flixtrain, RegioJet, and Leo Express â reinforced our desire to enter this market.
And this was all despite warnings from experts from the very start. âLegally, the market is open, but itâs dominated by legacy players,â they said. âYouâll never be able to find second-hand material because the historical players prefer to scrap it, rather than sell it to new entrants,â they said. âNo builder will agree to work with a small company like yours,â they said. âNo one will finance your rolling stock because the unsubsidised passenger market is considered risky,â they said. âItâs hellish to work with infrastructure managers who are under the thumb of the historic national operators,â they said. âIt could work elsewhere in Europe, but the French railway belongs to the SNCF and public actors protect it,â they said. And those are just some of the things we heard.
Weâre well aware of all these risks. But we measured them and evaluated them. Building on other agenda-setting, successful experiences in other sectors, we saw a path that was tentative, but realistic, to achieve the end goal. We wanted to find solutions to this complicated equation rather than stopping at the hurdles, at first glance, and deciding they couldnât be overcome.
It all started with fundraising which enabled us to develop the project. A fundraising effort that we carried out with more than forty business angels who were just as passionate about the project as us. Together, we defined the major goals needed to take the next step. It took us two years to achieve them. They were two difficult years during which we learned to think, speak and live railways, which enabled us to create relationships of trust with all the major players in the sector.
It was also at the end of those first two years that Nicolas Bargelès, our wonderful, daring director of operations and new partner, joined us.
With an entire founding team, the trains ready to be built (with the technical specifications and design carried out), a carefully selected manufacturer and an English leaser on our side to finance the first two trains, we then tackled our second fundraising, which would allow us to launch, at a minimum, our first Paris-Milan-Venice line.
And this is where we fell down.
We could spend hours telling you the whole story, but it’s all in the archive: Confidences. We will try to take stock here, with the hindsight and foresight necessary for this type of exercise.
1: We believed that our vision would be shared more widely by financiers
We built our conviction around a strong hypothesis thatâs still fair in our eyes: there would be no âcleanâ aeroplane before the end of the century and the only way to decarbonise medium-haul travel is the night train. However, the night train in its current form, and for the next decade, wonât live up to instigating the shift thatâs required.
We had the impression that this vision would be shared by as many people as possible. On this point, we were correct and as soon as the creation of our company was announced, thousands of people joined us around this vision. However, we hadnât taken into account two killer factors, which are below.
Rail isnât a âmega trendâ and night trains even less so: Itâs possible, in our time, to finance and launch large-scale industrial projects with the objective of protecting the environment. However, these sectors are restricted by public authorities. This was the case a few years ago for the energy sector, then for food and agriculture. Off the beaten track, itâs almost impossible to get there. We should have realised quickly that the railway sector wasnât ready to open up to new private entrants. The money and energy of public authorities are concentrated on energy and in our case on clean aircraft more than on the uses or improving what already exists.
The reality of opening the market to competition: The channels are open, but in reality, the rail market has mainly opened up to itself. This market was organised by the public authorities for their own historical operators, not to really create new players. Each European country can see its neighbours land on its territory and vice versa. These operators have the goods (rolling stock) and the means (financing and public guarantee bodies) to deploy. We knew this, but thought it would be possible to change the rules, or that they would evolve on their own. It was a poor reading on our part: we listened too closely to the claims, but didnât look enough at the actions of the French and European public authorities.
2: Financial players in Europe arenât in line with a project like Midnight, its risk profile, maturity, ambition and characteristics
On the one hand, seed funds (venture capitalists) donât invest in long-term projects with assets to operate. Itâs a shame, because they know how to support entrepreneurs in their first years.
On the other hand, infrastructure funds donât invest in young companies and have very little interest in rail. Itâs a shame, because they know how to invest in long-term companies with significant assets under management.
And finally, growth funds invest in growth and rarely take the commercial risk of starting a business. Itâs a shame because some of them have a VC culture and others the culture of infrastructure.
The remit was tight, we had few obvious targets and lots of elements to synchronise. With bad timing, bad tempo, and a lack of success, we failed to create the momentum we needed. However, fundraising is the key to it all.
3: Not sufficiently funded from the start, we lacked velocity and didnât reach the necessary maturity
We should have stopped when we failed to raise the âŹ5 million needed in our first round. We thought at that time that with the financial efforts and energy of the founders, we could move mountains. Unfortunately, we werenât strong enough to tackle this extraordinary, unprecedented second round of funding. With a total of âŹ1.3M, even without paying ourselves, it was impossible to align additional subjects with the specification of our trains, the partnership with a manufacturer, the specification of our IS, to find a director of operations and community building.
With more cash, we could have:
⢠Obtained our railway company licence and safety certificate, which would have strengthened our file, particularly with investors who werenât experienced in the sector.
⢠Mandate an independent consulting company to challenge our business plan and, in particular, our traffic hypotheses. A document like this costs between âŹ300,000 and âŹ500,000 and weâve always refused to invest them. To this day, we regret that.
⢠Hire a lobbying team. We thought that after the texts and declarations, a company like ours could be useful to administrations and politicians to take action. We also thought that the current French government, which is pro start-ups, would have liked to demonstrate that each sector must be open to innovative companies.
⢠Grow the team more quickly and rent offices. It’s surface-level and correlated with everything else, but a larger team and offices would have given an impression of solidity and maturity to our interlocutors when the ultimate decision needed to be made. It was unnecessary at this stage, but would have given us a better image.
We have always made measured choices, as good fathers, and perhaps we should have thought bigger, faster, or stopped sooner.
So yes, the railway sector is quite exclusive, complex and rigid, but we were well received and fell in love with this extraordinary world thatâs been built with passion by enthusiasts. We warmly and kindly thank everyone we had the chance to meet and everyone we worked with.
We really hope that in the coming years, the European Commission, the governments of the Member States, as well as the organising authorities, will build a railway capable of welcoming new innovative companies. We hope that this dynamic will allow investment funds to take an interest in rail, so that other entrepreneurs can succeed in creating new uses and improving the train travel experience. To make this means of transport beloved as a significant alternative to aviation and automobiles.
On a more personal note, we regret having proved right some of the sceptics and cynics that we encountered in the public and private sector during the past four years. But above all we regret having generated so much hope and desire among the general public, among you, the readers, who have been following our progress. We also regret not having succeeded in bringing to life a product that we dreamed of so much. Dreams are meant to be realised, and weâve failed to make this one a reality.
Let’s keep dreaming of Midnight Trains. One day, other entrepreneurs may succeed where we failed. And so much the better, the planet needs it. If certain entrepreneurs wish to save time and start from a healthy, established basis to launch a similar project, weâre open to discussion for the transfer of our assets.
Thank you all for sharing our dream and believing in us to make it come true.
Goodnight all.
Adrien, Romain and Nicolas
More on night trains and transcontinental train travel
- Arriva Tri-Country Train between Maastricht, Liège and Aachen will start on Sunday 9 June 2024 without OV-chipkaart.
- European Sleeper finally connects Belgium and the Netherlands to Berlin, Dresden and Prague.
- Slow(er) Eurocity Brussels â Mons â Paris for Olympic and Paralympic Games in July and August 2024.
- Brussels to Luxembourg by train under 2 hours by 2030?.
- GoVolta wants tourist trains from the Netherlands to Berlin, Paris and Basel and from Antwerp to Germany.
- Heuro wants to operate high speeds trains between Amsterdam, Antwerp, Brussels, Paris and London from 2028.
- Eurostar and five more train operators joined the European Agreement on Journey Continuation.
- ĂBBâs new Nightjet sleeper cars accommodate solo travellers with Mini Cabins.
- Trenitalia orders new Hitachi Frecciarossa trains suited for France, Belgium and the Netherlands.
- ĂBBâs Nightjet to connect Berlin to Brussels from December 2023.
- EUROCITY EC-8 | Basel to Cologne in SBBâs Panoramic Car.
- Trenitalia / FS confirms interest in connecting Spain to Brussels, Amsterdam and Berlin.
- Deutsche Bahn and Trenitalia want piece of Amsterdam â Brussels â Paris HST service via subsidiaries Arriva an Qbuzz.
- SNCF and NMBS / SNCB to link Paris to Brussels with âslowâ classic train in about 3 hours from December 2024.
- Sampling NSâ new train and future Benelux rolling stock ICNG.
- REVIEW | Trenitalia Frecciarossa 1000 Paris â Milan in Business Executive.
- RAIL TOUR OF EUROPE | How easy is touring Europe by train?.
- Eight train connections between the Netherlands and Belgium by 2030?.
- REVIEW | ĂBB Nightjet Amsterdam â Zurich night train.
- European Commission wants booking train tickets to be as easy as booking flights.
- Nightjet Vienna/Innsbruck to Brussels, or how we got thrown off the train in Aachen.
- Why the expensive ĂBB Nightjet is really not that expensive.
- Reliving the era of the great railway journeys, travelling overnight on Nightjet.
- How we plan a big rail trip.
- Ticket Distribution: the failure of railways to sell themselves.
- To use night trains in Portugal and Spain or not?.
- Night trains in Europe.
- Low-cost, long-haul trains to conquer Europe?.
- Fly now before itâs taxed and consider using the train instead.

13 Comments Add yours